Progress with works on the Rakova Jelša II residential neighbourhood
8. Sep 2021
At our construction site, the Rakova Jelša II residential neighbourhood, which consists of five residential and one multi-purpose facility, we are progressing with work according to the schedule.
The rough construction of the last residential building is currently being completed, and the foundation slab for the multi-purpose building has already been completed. In other buildings, the façade is lined with clinker tiles, and dry-assembly work is being finalized inside. The installation of screeds, installation of elevators, painting and ceramic works are in progress.