Rehabilitation of Poljane elementary school
12. Aug 2019
At the end of May 2019, we started works on the Poljane elementary school for the MOL investor.
As part of the renovation, we are carrying out a comprehensive fire safety and static rehabilitation of the building. Static rehabilitation of the existing load-bearing structure is performed by adding reinforced concrete walls, applying FRG plasters and adding steel frames, which are founded with the help of spirally drilled piles inside the building. Despite demanding and extensive interventions, the work is progressing successfully and will be completed by the end of August 2019. Finishing construction works are currently being carried out on the facility.