The swimming pool in Radovljica is already getting a new look

8. Sep 2022
This time we are reporting from the construction site in Gorenjska, where we are reconstructing the swimming pool in Radovljica for the Municipality of Radovljica.

Extensive works are underway these days

  • on the assembly of joinery and facade glazing,
  • a roof is being built on the teaching pool, which will actually be the bar's terrace and a place for deckchairs. Part of the roof will be in ceramic, and part of the roof will have wooden flooring.
  • laying ceramics in the facility of the Olympic swimming pool in the machine rooms and dressing rooms,
  • sanding the lower platform between the two objects,
  • hardware installation of pool technology is carried out,
  • extensive work on electrical installations is also underway,
  • and other auxiliary construction works.